Structural
Repairs to Samson V in 2001
In June 2001, core samples
taken from Samson V's hog posts and A-frame indicated several potential
structural deficiencies. In July, a professional engineer determined that the
A-frame posed an immediate threat to public safety, and the Museum closed down
temporarily for repairs. Samson V was towed to Fraser River Pile
and Dredge's docks to have the A-frame removed.
|
A-frame after replacement
|
 |
Removing
the A-frame
A cable from a crane was attached to the A-frame's headpiece to take up the slack
and provide support. First, the compression stays running down the outboard side
of the A-frame legs were cut (it was impossible to release them); then, a second
crane supported the port backstay, while the fastening pin at the aft end was
pounded out of the king post cap. This procedure was repeated for the starboard
backstay.
|
When
tension was released on the starboard backstay, the A-frame legs broke immediately
above the steel knees (which fasten them to the ship's deck). With tension maintained
on the A-frame, the legs were cut at the break and the A-frame was hoisted off
the ship and laid down on the dock.
|
 |
It was hoped that some of the timber used in the A-frame's legs could be salvaged
and reused in other phases of the restoration project; however, both legs were
rotten in their cores all the way to the top two or three feet. The timber was
disposed of, and the A-frame headpiece was hoisted back aboard the vessel for
later analysis and restoration.
Top
of Page
Prep
Work
Samson V was returned to her dock and work proceeded on the restoration
of the A-frame headpiece. All components were removed, numbered and individually
prepped and repainted with two coats of black Tremclad anti-rust enamel.
Many of the bolts were
bent from the accumulated loads and had to be replaced, but the main blocks were
found to be in good shape, as was the steel sheathing of the headpiece.
The timber component of the headpiece, however, was completely rotten. New A-frame
timbers were ordered from Fibretech Select Forest Salvage, specifying mast-and-spar
quality coastal Douglas fir, free of heart content.
|

A-frame knees before repairs
|

A-frame knees after repairs
|
The A-frame knees were
then removed and the partners upon which they rest were photo-documented and thoroughly
prepped. Rotten sections of the partners, which were made of yellow cedar, were
cut out and yellow cedar fillets installed in their place.
Three of three four gumwood
shims that level the A-frame knees against the sheer-line of the deck were too
deteriorated to be reused, so new shims were fabricated out of purple-heart, thoroughly
treated with copper napthanate and creosote, and installed in their place prior
to re-bolting the steel knees.
|

Future A-frame
|

Assembling A-frame
|
Top of Page
The Hog Posts
Work then proceeded on restoring the failing components of Samson V's
hog post system. The forward starboard hog post was previously determined to have
rotted extensively throughout the upper five feet of its length. It was decided
that replacing this post in its entirety would be more reliable and cost-effective
than applying a sectional repair. A new post of Douglas fir creosoted to 16 lbs
retention was ordered from Stella-Jones in New Westminster.
A primary
concern when disassembling the hog post system for repairs was avoiding new loads
being imposed on the vessel when slacking-off the hog rods. A cable was fastened
to the forward starboard mooring cleat and run to the king post at the underside
of the boat deck. This was tensioned with a come-along, until it was evident that
strain had been taken off the forward starboard hog rod.
|
 |
The forward hog rod was
then slacked off at the turnbuckle and the pin securing it to the hog post cap
driven out. The hog rod was then lowered to the deck for prep-work and painting.
In order to remove the hog post, the support bar for the A-frame backstay had
to be unbolted. The support bar was supported by a 2x6 and stayed with ropes while
the carriage bolts were removed.
|
|
When the pin fastening
the hog rod leading aft from the post was removed, and the hog rod supported,
the hog post cap was lifted off, prepped and painted.
A spreader-bar made from
steel pipe fits between the forward hog posts. Tension is maintained by means
of a steel rod that runs inside the pipe and through the posts. The hog post was
secured with ropes and the nut on the steel rod was removed and the rod pounded
through. The hog post was then lowered to the deck by means of a block and tackle.
|
The measurements for the
cuts around the end cap were taken from the old hog post and applied to the new
timber. All the cuts were made and the timber was then primed and painted. As
expected, creosote began to bleed through almost immediately. A coat of spar varnish
was applied, and a final topcoat stopped the bleed-through for the time being.
Regular painting will be necessary for the next few years, until the creosote
stabilizes.
Completed starboard hog
post
scarf joint
|

Forward hog post down with
new one ready to go up |
The new hog post was raised
into position with a block and tackle and the restored cap piece installed. Bolt
holes were drilled with the timber in place and the spreader-bar and A-frame backstay
support bar were re-attached.
With the cable run forward from the king post to the forward starboard cleat,
a second cable was attached to the king post immediately above the boat deck level
and run to the aft starboard hog post. This was tensioned with a come-along and
fastened into place.
With strain taken off the hog rods running to the king post, it was then possible
to slacken them using their turnbuckles, without altering the stresses on the
hull.
Plywood was laid down to protect the deck canvas near the king posts, scaffolding
was set up around the starboard king post, and a strong-back fitted above the
cap piece. The block and tackle was suspended from the strong-back and used to
lift the upper set of hog rods together. These were laid aside on the deck for
prep-work and painting. The inner set of hog rods was disconnected and the cap
piece was lifted off.
A support structure was built for the king post tie beam and fitted so it could
take its weight. Then the nut was removed from the tensioning rod running immediately
below the tie beam, and the rod was driven back through the king post and suspended
from the tie beam.
Top of Page